Change Order/Contract Increase: Downtown Raised Crosswalk and Spot Drainage Improvements
Summary Recommendation
Authorize a change order/contract increase to the approved construction contract with Gutierrez Canales Engineering, PC (GCE), in the amount not to exceed $2,926.48 for construction services for Downtown Raised Crosswalk and Spot Drainage Improvements. (Engineering) (Jeffrey A. Kramer)