Legislation Details

File #: MC 2026-105    Version: 1 Name:
Type: motion Status: Agenda Ready
File created: 5/26/2026 In control: City Council Meeting
On agenda: 6/17/2026 Final action:
Title: Ratification: Water Distribution Line, Gila Street to Redondo
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

 

STRATEGIC OUTCOMES

ACTION

Department:

Safe & Prosperous

Motion

Finance

Active & Appealing

Resolution

 

Respected & Responsible

Ordinance - Introduction

Division:

Connected & Engaged

Ordinance - Adoption

Procurement

Unique & Creative

Public Hearing

 

TITLE:

title

Ratification: Water Distribution Line, Gila Street to Redondo

 

end

 

SUMMARY RECOMMENDATION:

Summary Recommendation

Authorize the ratification of a purchase order for jack and bore obstruction delays for the 5th Street Water Distribution Line, Gila Street to Redondo Road Project, in the amount of $173,229.66 to Taylor Engineering, Yuma, Arizona. (Engineering RFB-25-283) (Dave Wostenberg/Robin R. Wilson)

 

end

 

STRATEGIC OUTCOME:

Ratification of this change order supports the City Council’s strategic outcome of Safe and Prosperous by ensuring the project continued without delay and without the significant cost increases that would have occurred if the work had to be rebid and completed later. Keeping the contractor on site avoided additional mobilization costs, prevented exposure to rising material and labor prices, and maintained construction momentum. By preserving resources and keeping critical water-infrastructure improvements on schedule, this action directly contributed to a safer, more reliable, and more prosperous community.

 

REPORT:

On January 7, 2026, City Council authorized the bid award for this project in the amount of $1,381,777.00 to Taylor Engineering. During the jack and bore process, an unexpected obstruction was found beneath the Union Pacific Railroad right of way. This required immediate coordination among Union Pacific Railroad (UPRR), RailPros, and several City departments. To comply with UPRR’s strict requirements, Taylor Engineering submitted work-plan variances, introduced extra safety measures, and organized the removal of the obstruction to keep the project moving forward.

This response ensured that the jack and bore operation could proceed safely, protected existing railroad infrastructure, and maintained regulatory compliance. The obstacle had the potential to significantly impact the schedule and create risks, but resolving it quickly enabled the contractor to continue working without demobilizing or incurring expensive delays.

Thanks to these efforts, only two additional weeks were added to the schedule, safety standards were upheld, and all railroad operational requirements were met, supporting the successful completion of this important water-infrastructure upgrade.

 

 

 

 

 

FISCAL REQUIREMENTS:

CITY FUNDS:

$ 173,229.66

BUDGETED:

$ 0.00

STATE FUNDS:

$ 0.00

AVAILABLE TO TRANSFER:

$ 173,229.66 

FEDERAL FUNDS:

$ 0.00

IN CONTINGENCY:

$ 0.00

OTHER SOURCES:

$ 0.00

FUNDING ACCOUNT/FUND #/CIP:

TOTAL

$ 173,229.66

Water Fund

 

FISCAL IMPACT STATEMENT:

FY 2026 Budget authority is available to transfer from other Water utility capital projects without impacting those projects’ completion or Water utility operations.

 

SUPPORTING DOCUMENTS NOT ATTACHED TO THE CITY COUNCIL ACTION FORM THAT ARE ON FILE IN THE OFFICE OF THE CITY CLERK:

 

NONE

 

IF CITY COUNCIL ACTION INCLUDES A CONTRACT, LEASE OR AGREEMENT, WHO WILL BE RESPONSIBLE FOR ROUTING THE DOCUMENT FOR SIGNATURE AFTER CITY COUNCIL APPROVAL?

 

Department

City Clerk’s Office

Document to be recorded

Document to be codified

 

Acting City Administrator:

Date:

John D. Simonton

06/09/2026

Reviewed by City Attorney:

Date:

Richard W. Files

06/08/2026