Legislation Details

File #: MC 2026-185    Version: 1 Name:
Type: motion Status: Agenda Ready
File created: 9/14/2026 In control: City Council Meeting
On agenda: 10/7/2026 Final action:
Title: Ratification: Water Distribution Line, Gila Street to Redondo Center Drive, Change Order No. 2
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

                                                   

 

STRATEGIC OUTCOMES

 

ACTION

Department:

X

Safe & Prosperous

X

Motion

Finance

 

Active & Appealing

 

Resolution

 

 

Respected & Responsible

 

Ordinance - Introduction

Division:

 

Connected & Engaged

 

Ordinance - Adoption

Procurement

 

Unique & Creative

 

Public Hearing

 

TITLE:

title

Ratification: Water Distribution Line, Gila Street to Redondo Center Drive, Change Order No. 2

end

 

SUMMARY RECOMMENDATION:

Summary Recommendation

Authorize the ratification and approve a change order for additional asphalt pavement, curb and gutter work associated with the 5th Street Water Distribution Line, Gila Street to Redondo Project in the amount of $99,763.07 to Taylor Engineering. (Engineering RFB-25-283) (Dave Wostenberg/Robin R. Wilson)

 

end

 

STRATEGIC OUTCOME:

Ratification of this change order supports the City Council’s strategic outcome of Safe and Prosperous by ensuring the City’s water infrastructure is safe, reliable and capable of meeting current and future demands. Change Order No.2 addressed an unforeseen field condition related to the location of the existing watermain and provided the necessary modifications to safely complete the connection and successfully deliver the project.

 

REPORT:

On January 7, 2026, City Council authorized the bid award for this project in the amount of $1,381,777.00 to Taylor Engineering. On June 17, 2026, City Council authorized a $173,229.66 change order due to the jack and bore process with an unexpected obstruction found beneath the Union Pacific Railroad.

 

As the project progressed, the construction plans depicted existing 16-inch polyvinyl chloride water main west of Redondo Center Drive. Multiple potholing attempts did not locate the main at the depicted location. Additional field investigation confirmed that the main was beneath the Redondo Center Drive roadway.

 

This unforeseen differing site condition required the proposed tie-in excavation to extend beyond the anticipated work area and original construction footprint assumed during bidding. The expanded work required additional watermain pipe, asphalt pavement and curb-and-gutter restoration. Taylor Engineering implemented the necessary modifications with the approval from City staff and completed the project work with the final change order total of $99,763.07 which is presented for ratification and approval.

 

The new contract value following Change Order No. 2 is $1,654,769.73.

 

 

 

 

FISCAL REQUIREMENTS:

CITY FUNDS:

$99,763.07

BUDGETED:

$1,381,777.00

STATE FUNDS:

$ 0.00

AVAILABLE TO TRANSFER:

$99,763.07

FEDERAL FUNDS:

$ 0.00

IN CONTINGENCY:

$ 0.00

OTHER SOURCES:

$ 0.00

FUNDING ACCOUNT/FUND #/CIP:

TOTAL

$99,763.07

2025 CIP Bonds: Water Fund 

 

FISCAL IMPACT STATEMENT:

Sufficient budget capacity is provided in the FY 2027 City Council approved budget to ratify and approve this change order.

 

ADDITIONAL INFORMATION:

SUPPORTING DOCUMENTS NOT ATTACHED TO THE CITY COUNCIL ACTION FORM THAT ARE ON FILE IN THE OFFICE OF THE CITY CLERK:

 

NONE

 

IF CITY COUNCIL ACTION INCLUDES A CONTRACT, LEASE OR AGREEMENT, WHO WILL BE RESPONSIBLE FOR ROUTING THE DOCUMENT FOR SIGNATURE AFTER CITY COUNCIL APPROVAL?

 

 

Department

 

City Clerk’s Office

 

Document to be recorded

 

Document to be codified

 

Acting City Administrator:

Date:

John D. Simonton

09/29/2026

Reviewed by City Attorney:

Date:

Richard W. Files

09/28/2026