Title: Intergovernmental Agreement: Off System Bridge Funding - 3rd St. Bridge at East Main Canal
Attachments: 1. 1. RES IGA for Off System Bridge Funding- 3rd St Bridge at East Main Canal, 2. 2. AGMT IGA for Off System Bridge Funding- 3rd St Bridge at East Main Canal

 

 

STRATEGIC OUTCOMES

ACTION

Department:

Safe & Prosperous

Motion

Engineering

Active & Appealing

Resolution

 

Respected & Responsible

Ordinance - Introduction

Division:

Connected & Engaged

Ordinance - Adoption

Engineering

Unique & Creative

Public Hearing

 

TITLE: t

 

Intergovernmental Agreement: Off System Bridge Funding - 3rd St. Bridge at East Main Canal

 

end

 

SUMMARY RECOMMENDATION: Summary Recommendation

Authorize the City Administrator to execute an IGA with ADOT to receive Off System Bridge (OSB) funding, $143,807 of federal-aid funding, $8,693 of City funding, for a total amount of $152,500 for the scoping/preliminary design of the 3rd St. Bridge at the East Main Canal.  (Engineering) (David Wostenberg)

 

end

 

STRATEGIC OUTCOME:

Utilizing OSB funding for the preliminary design of the 3rd St. bridge meets the City Council’s strategic outcome of Respected and Responsible by utilizing the OSB program to help with administering and funding the improvement of the City’s existing infrastructure. The primary purpose of this project is the improvement of the efficiency, reliability, and safety of the traveling public.

 

REPORT:

The City of Yuma is utilizing the Arizona Department of Transportation’s (ADOT) OSB program to assist the City with funding and administering the 3rd St. Bridge at East Main Canal Preliminary Design project. The work proposed under this IGA consists of scoping services, 30 percent design plans, and estimates for improving the existing condition of the 3rd St. bridge. The project includes but is not limited to scoping of the substructure, abutments, approaches, pier walls and caps, expansion joints, bridge rail and bridge deck. Preliminary design also includes the determination of environmental and right of way requirements. The project cost is estimated at $152,500, which includes federal aid and the City’s match.  In addition to the City’s $8,693.00 contribution to the project cost, any amounts over the estimated project cost must be paid by the City.

 

Final design and construction will be addressed in a separate agreement as applicable. 

 

 

FISCAL REQUIREMENTS:

CITY FUNDS:

$ 8,693.00

BUDGETED:

$ 152,500.00

STATE FUNDS:

$ 0.00

AVAILABLE TO TRANSFER:

$ 0.00

FEDERAL FUNDS:

$ 143,807.00

IN CONTINGENCY:

$ 0.00

OTHER SOURCES:

$ 0.00

FUNDING: ACCOUNT/FUND #/CIP

TOTAL

$ 152,500.00

Grants-198 and City Road Tax-102

To total; right click number & choose “Update Field”

 

 

FISCAL IMPACT STATEMENT:

Approval of this preliminary design agreement will have a financial impact on the city of $8,693. If the bridge is not repaired the continued maintenance of this structure will have a significant financial impact on the City.

 

 

ADDITIONAL INFORMATION:

SUPPORTING DOCUMENTS NOT ATTACHED TO THE CITY COUNCIL ACTION FORM THAT ARE ON FILE IN THE OFFICE OF THE CITY CLERK:

 

NONE

 

 

IF CITY COUNCIL ACTION INCLUDES A CONTRACT, LEASE OR AGREEMENT, WHO WILL BE RESPONSIBLE FOR ROUTING THE DOCUMENT FOR SIGNATURE AFTER CITY COUNCIL APPROVAL?

 

Department

City Clerk’s Office

Document to be recorded

Document to be codified

 

Acting City Administrator:

Date:

John D. Simonton

01/27/2025

Reviewed by City Attorney:

Date:

Richard W. Files

01/27/2025